New Building Construction Update 2/18/2019

February 19th, 2019 by

Footings continue! Strip footings have been poured along the north and south column lines. We have also added new curbing along the back of the property in preparation for the future battery building.

Construction site preparation featuring excavation

Preparation starts with excavating to the proper width and depth. Rebar is tied and placed in the excavation to provide the concrete with additional support.

Collage of concrete placement in the excavation

Concrete has been placed into the excavation. Here is a look at the northern column line.

Collage showing the drive and parking lot progress

The future drive and parking lot has been stoned and compacted.

Collage of pavement demo and curbing preparations

Existing asphalt has been demo’d at the rear of the site in preparation for the future battery building. New curbing has already been installed for the adjacent parking island.

Upcoming Construction

Upcoming Week Look Ahead:

  • Finalize building footings
  • Prepare and pour elevator pit
  • Electrical and plumbing undergrounds
Posted in New Facility