August will be a huge month at Baker Porsche. The past week has included some major utility work and the first steps towards the storefront glass installation. With ceilings being framed, the scene will begin to quickly change.

 

 

One last bit of coordination in the sales area prior to framing the hard ceilings. All lighting and mechanical fixtures were laid out to assist the framing crew.

 

 

In just a few days, the ceilings were framed in. We’ll wrap up the last of overhead inspections and begin hanging drywall.

 

 

A new fire hydrant and transformer both set in a week! Plenty of work going on inside and out.

 

 

Standard Glass has arrived at full force. The track for the finwall system was installed this week, which means we can start looking towards storefront glass!

 

Upcoming Construction

  • Continue Finwall install
  • Skylight delivery and install
  • MEP overheads in the shop
  •  Begin hanging gypsum board

 