Construction Update 4/3/2020

April 7th, 2020 by

Baker Collection

Collection Update 4/3/2020

Sales building steel erection has completed and framing is underway. Ductwork has begun and we now look for roofing and rough-ins to begin. Service building erection continues as wall panels are installed and roofing begins.

Sales Building 

Steel and roof decking has completed for the sales building. This allowed for interior mechanical work to begin and TPO roofing to begin on top of the decking.

Above: Grey Interiors has completed exterior framing and door frames were delivered and installed by East Coast Access.

Below: Interior framing install continues and ductwork install has begun.

Service Building

 

Service building erection by Waterpointe has quickly progressed on site with wall panels and roofing having started this week. Next, simple saver insulation will be installed.

Site

The front parking area was recently completed for an early turnover to enable the owner to begin use. MSB Development was a key player in this turnover. Thanks to MSB for the hard work!

Looking Ahead

Service Building:

  • Complete metal building erection
  • Begin simple saver insulation
  • Begin carwash CMU

Sales Building:

  • Complete interior framing
  • Complete exterior sheathing
  • Continue ductwork install
  • Begin TPO roofing
  • Begin electrical and plumbing rough-ins
Posted in New Construction