New Building Construction Update 08/19/2019

August 19th, 2019 by

Drywall, glass, and metal panels have arrived and are well into installation. We will continue to bring in more trades to help with finishes as August progresses. The building is quickly coming together and everyday brings forth exciting, new changes.     The store front glass and finwall arrived on site last week and Standard…

Posted in New Facility

New Building Construction Update 08/02/2019

August 7th, 2019 by

August will be a huge month at Baker Porsche. The past week has included some major utility work and the first steps towards the storefront glass installation. With ceilings being framed, the scene will begin to quickly change.     One last bit of coordination in the sales area prior to framing the hard ceilings….

Posted in New Facility

New Building Construction Update 07/26/2019

July 29th, 2019 by

The rough-in phase is coming to an end! Mechanical, electrical, and plumbing trades have worked hard to obtain the necessary inspections. We’re excited to close in ceilings and walls and start installing glass!     We started the week off with plenty of excitement. Six rooftop units arrived and were set on the roof. Only…

Posted in New Facility

New Building Construction Update 07/18/2019

July 26th, 2019 by

The exterior of the building has been insulated and rough-ins are nearing completion! Trades have been battling the heat to ensure inspection milestones are met. Standard Glass is onsite, making great progress on storefront curtain wall and clerestory window frames in the shop area. Grey Interiors has completed exterior insulation, allowing all exterior metal scans…

Posted in New Facility

New Building Construction Update 6/24/2019

June 24th, 2019 by

Things at Baker Porsche Wilmington continue to heat up. More trades and materials continue to arrive at the site. Now that the stairs are installed, we’ll begin to see the second floor gain more momentum. The front radius wall is continually changing. Waterproofing is complete and Grey Interiors is back at it. Two-inch foam insulation…

Posted in New Facility

New Building Construction Update 6/10/2019

June 10th, 2019 by

The sheathing is complete and our next step for this area is to finish waterproofing and begin insulating. That being said, it’s always nice to take a step back and observe the building coming into shape. Framing is underway at interior walls, exterior walls, hard ceilings, and even the skylights. At this point in time,…

Posted in New Facility

New Construction Building Update 5/31/19

May 31st, 2019 by

Last week, the final joists were set in the shop area. Fast forward less than a week and decking has completely covered the back of the house. Here’s what the decking operation looks like from above. Decking is welded directly to the joists below and despite the immense heat, blinding reflections, and maybe some acrophobia,…

Posted in New Facility

New Building Construction Update 5/23/2019

May 17th, 2019 by

The final joists have been set in the shop area. Our steel trade partner will spend another week adding roof decking and fine-tuning the structure. Then, the erection will officially be complete. “Radius Framing, Made Easy” by Grey Interiors. Framing a curved wall has historically brought forth a few challenges. Instead, Grey Interiors has arrived…

Posted in New Facility

New Building Construction Update 5/9/2019

May 14th, 2019 by

If you enjoy welding, now is a good time to visit Wilmington Porsche. Steel erection is rolling fast to beat the summer heat. We’re excited to wrap up steel in the front of house, opening up the showroom for more trades. The front radius has successfully wrapped around to the north and south walls of…

Posted in New Facility

New Building Construction Update 5/1/2019

May 9th, 2019 by

Steel on the move! Steel erection continues to wrap around the front radius and bring the storefront and showroom to life. Here’s a look at the front of the house! We have a packed lay-down yard with materials, a crane, and lifts everywhere! It will be exciting to see the material installed and the yard…

Posted in New Facility
Saved
Saved Vehicles ×

SAVED VEHICLES

You don't have any saved vehicles!

Look for this link on your favorites:

Save

Once you've saved some vehicles, you can view them here at any time.

Contact
Contact Us ×

(910) 777-7732

Call Now

4920 New Centre Dr • Wilmington, NC 28405

Get Directions

Today's Hours:

Sales: Closed

Service: Closed

Parts: Closed

Porsche Wilmington

4920 New Centre Dr Wilmington, NC

Phone:

https://goo.gl/maps/W4EmDuCzTJ92

Sales

Phone: (910) 777-7732

4920 New Centre Dr Wilmington, NC
34.24196 -77.879812
[schema type="organization" orgtype="LocalBusiness" url="www.porschewilmington.com" name="Porsche Wilmington" description="" street="4920 New Centre Dr" city="Wilmington" state="NC" postalcode="28405" country="US" email="tcoyle@porscheofwilmington.com; jwade@porscheofwilmington.com;" phone="" logo="https://di-uploads-development.dealerinspire.com/porschewilmington/uploads/2018/06/PorscheWilmingtonOGImage-1.png"]
Porsche Wilmington
Porsche Wilmington
4920 New Centre Dr
Wilmington, NC, 28405 US
https://di-uploads-development.dealerinspire.com/porschewilmington/uploads/2018/06/PorscheWilmingtonOGImage-1.png
Porsche Wilmington 34.24196, -77.879812.