New Building Construction Update 4/11/2019

April 12th, 2019 by

Construction over the last week consisted of running underground sewer and water lines, finalizing rough-ins, and placing the vapor barrier. We are creeping up on the milestone of a slab pour. Utilities have been run from the northwest corner of the building and around the corner to Hunt Club Drive. It was a tight squeeze,…

Posted in New Facility

New Building Construction Update 4/1/2019

April 3rd, 2019 by

Electrical and plumbing rough-ins are popping out of the ground. Work has moved towards the front of the building towards New Centre Drive. The shop area is ready for slab prep and the show room area should be wrapping up shortly. Electrical conduit has been sleeved from the shop to the front of house. Plumbing…

Posted in New Facility

New Building Construction Update 3/25/2019

March 27th, 2019 by

Wrapping up exterior CMU walls and beginning underground rough-ins has been our highlights as of late. Masonry has been rolling, with plumbing and electrical right behind. All trades are working hard to get the slab ready. Masons have wrapped up the majority of exterior walls and have started turning towards interior CMU walls. The north,…

Posted in New Facility

New Building Construction Update 3/11/2019

March 20th, 2019 by

We have officially gone vertical! Masonry is unstoppable, in wall rough ins are set throughout, and we continue to look ahead. Scaffolding began arriving early in the week and was set up along the south wall. By the end of the week, masons were already setting up the third level. With the help of a…

Posted in New Facility

New Building Construction Update 3/4/2019

March 7th, 2019 by

All footings have been poured and masonry has been cut loose! We’re excited to have more trades and materials arriving to the site. Over the course of this week, expect to see concrete block walls get quite a bit taller. The elevator pit floor and walls are complete! Concrete has been in and out of…

Posted in New Facility

New Building Construction Update 2/18/2019

February 19th, 2019 by
Collage of the Porsche Wilmington construction

Footings continue! Strip footings have been poured along the north and south column lines. We have also added new curbing along the back of the property in preparation for the future battery building. Preparation starts with excavating to the proper width and depth. Rebar is tied and placed in the excavation to provide the concrete…

Posted in New Facility

New Building Construction Update 2/11/2019

February 18th, 2019 by
A construction worker overseeing construction at Porsche of Wilmington

Construction underway! We are excited to break ground on the new Porsche Dealership coming to Wilmington. We are already moving at full speed, with no plans of slowing down. The building has been brought to grade, footings have been poured, and new curbing is in. Step one was bringing in more fill material and getting…

Posted in New Facility

Best Road Trip Games for Your Holiday Travels in Your Porsche Macan

December 15th, 2018 by

The holiday season has arrived! As you’re packing your Porsche Macan for this year’s family road trip from Wilmington, plan to play these favorite classic road-trip games on the way to your destination. Bonus? They’re fun for all ages, even your toddling car riders. 1. The License Plate Game: Can you spot a car from…

Posted in Uncategorized

Porsche Wilmington Construction Update 11/13/2018

November 16th, 2018 by

Underground gas lines have been capped and re-rerouted for the brand new Porsche Wilmington! Next to come is the final hauling so that there will soon be a vacant lot ready for a new building.  All that remains is what once was a building. The footers below ground have officially been removed and all that…

Posted in New Facility

Porsche Wilmington Construction Update 10/26/18

October 30th, 2018 by

Demolition is underway in preparation for the brand new Porsche Wilmington! So far, the majority of the old BMW building and the entire canopy has been removed to may way for the new Porsche building. Demolition started with the landscaping and existing storefront. Building materials were separated for proper disposal and hauled off to the…

Posted in New Facility
Saved
Saved Vehicles ×

SAVED VEHICLES

You don't have any saved vehicles!

Look for this link on your favorites:

Save

Once you've saved some vehicles, you can view them here at any time.

Contact
Contact Us ×

(910) 777-7732

Call Now

4920 New Centre Dr • Wilmington, NC 28405

Get Directions

Today's Hours:

Open Today! Sales: 9am-7pm

Open Today! Service: 7am-6pm

Open Today! Parts: 7:30am-6pm

Porsche Wilmington

4920 New Centre Dr Wilmington, NC

Phone:

https://goo.gl/maps/W4EmDuCzTJ92

Sales

Phone: (910) 777-7732

4920 New Centre Dr Wilmington, NC
34.24196 -77.879812
[schema type="organization" orgtype="LocalBusiness" url="www.porschewilmington.com" name="Porsche Wilmington" description="" street="4920 New Centre Dr" city="Wilmington" state="NC" postalcode="28405" country="US" email="tcoyle@porscheofwilmington.com; jwade@porscheofwilmington.com;" phone="" logo="https://di-uploads-development.dealerinspire.com/porschewilmington/uploads/2018/06/PorscheWilmingtonOGImage-1.png"]
Porsche Wilmington
Porsche Wilmington
4920 New Centre Dr
Wilmington, NC, 28405 US
https://di-uploads-development.dealerinspire.com/porschewilmington/uploads/2018/06/PorscheWilmingtonOGImage-1.png
Porsche Wilmington 34.24196, -77.879812.