Schedule Appointment

Construction Update 4/3/2020

April 7th, 2020 by

Baker Collection Collection Update 4/3/2020 Sales building steel erection has completed and framing is underway. Ductwork has begun and we now look for roofing and rough-ins to begin. Service building erection continues as wall panels are installed and roofing begins. Sales Building  Steel and roof decking has completed for the sales building. This allowed for…

Posted in New Construction

Construction Update 3/12/2020

March 18th, 2020 by

Steel arrived on site this week for the Sales building and did not miss a beat to begin erecting. The service building slab has been poured and will soon have the metal pre-engineered building erection begin. Conduit for service building power has been run and our front parking lot is set for paving this week….

Posted in New Construction

Construction Update 3/2/2020

March 4th, 2020 by

Construction continues! The install of the new sanitary line is complete and concrete has been poured for the sales building slab. Site lighting conduit is nearing completion and pole bases are being set. Sales Building A big thank you to Caliber Associates for their commitment to getting this slab poured.   Service Building Service building…

Posted in New Construction

New Construction Update 2/10/20

February 10th, 2020 by

With demolition complete, stormwater piping has been installed, and building column lines surveyed and laid out. Sales building footings have been excavated, rebar placed and footing concrete poured. Plumbing and electrical underground rough-ins continue on both the sales and service buildings. Service Building Column lines for the service building have been laid out across the…

Posted in New Construction

New Building Construction Update 1/06/20

January 6th, 2020 by

Demolition continues on the site as both buildings have come down and the demo is now focused on the building slabs and old concrete footings. Service Building The service building slab demo began soon after materials from building demo were moved off site. Sales Building Macson’s made quick work of the sales building demo and…

Posted in New Construction

New Building Construction Update 12/13/2019

December 27th, 2019 by

Final photos are in! Porsche Wilmington has opened for business and Porsches are already on their way out the door. Thank you to Baker Motor Company and all trade partners who helped make this project a success. The Monteith Team is already gearing up for the next one. Nothing complements the front radius like some…

Posted in New Construction

New Building Construction Update 10/31/2019

October 31st, 2019 by

Halfway through the week and we’re turning the final corner at Baker Porsche Wilmington! Thank you to all of the trades who have continually pushed to get us here. Landscaping is wrapping up around the exterior of the building, final cleaners are hard at work on the interior, and all trades are wrapping up their…

Posted in New Construction

New Building Construction Update 10/12/2019

October 14th, 2019 by

The excitement continues to build at Baker Porsche Wilmington. All of the trades continue working relentlessly to help push towards the finish line. Over the past week, we saw major progress on the smooth panels, flooring barreled through the interior, and MSB Development mobilized to begin site work. AGI is back at it. Smooth panels…

Posted in New Construction

New Building Construction Update 10/04/2019

October 7th, 2019 by

It’s hard to believe that it’s already October. Trades put in a hard week, despite the mid-summer temperatures. We’re excited to see some smooth panels going up on the front radius. Finishes continue to move in and out of the building, while DPS keeps the pedal to the floor. October is off to a strong…

Posted in New Construction

New Building Construction Update 09/20/2019

September 23rd, 2019 by

Finishes are coming in! Tile and linear metal ceilings continue to run the interior of the building, while the exterior of the building continues to receive smooth and corrugated panels. All trades are gearing up for another beautiful week of work to close out September. Monday morning started off with a crane to set the…

Posted in New Construction
Saved
Saved Vehicles ×

SAVED VEHICLES

You don't have any saved vehicles!

Look for this link on your favorites:

Save

Once you've saved some vehicles, you can view them here at any time.

Contact
Contact Us ×

(910) 777-7732

Call Now

4920 New Centre Dr • Wilmington, NC 28405

Get Directions

Today's Hours:

Sales: Open for Online Business

Open Today! Service: 7am-4pm

Open Today! Parts: 7am-4pm

Porsche Wilmington

4920 New Centre Dr Wilmington, NC

Phone:

https://goo.gl/maps/W4EmDuCzTJ92

Sales

Phone: (910) 777-7732

4920 New Centre Dr Wilmington, NC
34.24196 -77.879812
Porsche Wilmington 34.24196, -77.879812.